As NexTier 3 wraps up their final pad with Chevron, the team leaves behind an incredible record of performance and safety. Here’s a look at the highlights shared during their farewell dinner:

  • Started with Chevron: 2017 (as Keene 3)
  • Water pumped: 200 million barrels
  • Sand pumped: 4.4 million tons
  • Pads completed: 104
  • Wells completed: 412
  • Stages completed: 18,033
  • Lateral footage: 3,210,000 feet (that’s about 607 miles!)
  • Project efficiency: 106%
  • Non-productive time (NPT): Just 8%
  • Incident-Free Operation (IFO): 795 days and counting

πŸ‘ Congratulations to the NexTier 3 team for finishing strong and setting a remarkable standard in performance, safety, and teamwork!

Commitment in Action

Commitment in Action

Bailey Istre showed exceptional dedication by stepping in on short notice for a twice-delayed offshore project. When the crew was sent home, he...

Read More
Limited Time SAVINGS

Limited Time SAVINGS

Protect your Crew- Pay Less! All things MSA on sale now until the end of September. As a certified partner with MSA, we can provide equipment, parts,...

Read More